New Construction Inspection Checklist: What to Check at Every Phase

Inspector with a flashlight checking plumbing and wiring in open wall framing of a new house

This guide contains affiliate links. As an Amazon Associate we earn from qualifying purchases, at no extra cost to you. Learn more.

In this guide
  1. City inspections vs. hiring a third-party inspector
  2. Phase 1: Pre-pour and foundation
  3. Phase 2: Framing
  4. Phase 3: Pre-drywall (MEP rough-in)
  5. Phase 4: Insulation
  6. Phase 5: Final inspection
  7. What to do when something fails or looks wrong
  8. Photo documentation tips
  9. Next steps

A good new construction inspection checklist follows the build in phases, because each stage hides the work of the one before it. Check the foundation before concrete, the framing and rough-ins before drywall, the insulation before it is covered, and everything again at final. Below is what to look for at each stage, how city inspections differ from hiring your own inspector, and how to document it all.

If you are running the job yourself, this list pairs with our guide on being your own general contractor. If a builder is doing the work, use it to know what to ask and when to show up.

City inspections vs. hiring a third-party inspector

Your permit triggers a series of required code inspections, typically including foundation, framing, rough mechanical, electrical and plumbing, energy or insulation, and final. These are performed by the city, or in some areas by the county or an approved third-party code inspection firm. They confirm the work meets the adopted code, which in most Texas cities is the International Residential Code (IRC) with local amendments. Check the current edition and amendments with your local permitting office, and see our overview of Texas building codes.

A code inspection is a minimum check, done on a schedule, by someone who may have many stops that day. A private inspector you hire works for you. They can spend more time, look at workmanship as well as code, and write a detailed report with photos.

City or code inspectionThird-party inspector you hire
Who they work forThe jurisdictionYou
Required?Yes, tied to your permitOptional
FocusCode complianceCode plus workmanship and details
ReportPass, fail or correction noticeUsually a written report with photos

In Texas, private home inspectors are generally licensed through the Texas Real Estate Commission (TREC). Ask for a license number, verify it on TREC's website, and ask whether the inspector has specific new construction phase experience. Some inspectors also hold ICC code certifications, which can be helpful for phase work. Fees vary by market and house size, so get a few quotes.

Phase 1: Pre-pour and foundation

Once concrete is poured, mistakes are set in stone, literally. Get on site after the forms, plumbing and reinforcement are in but before the pour.

  • Forms match the plan dimensions and the slab is positioned correctly relative to setbacks and the survey stakes.
  • Under-slab plumbing is in the right places for toilets, tubs, showers and the kitchen sink, and has been tested as required.
  • Vapor retarder is continuous, lapped and taped, with minimal tears.
  • Rebar or post-tension cables are placed per the engineer's design, supported on chairs rather than lying in the dirt.
  • Beam depths and widths look consistent with the foundation plan.
  • Drainage and grading direct water away from the slab area.

On expansive Texas clay soils, the foundation design from your engineer matters a great deal. Ask whether a post-pour or engineer's letter is required by your lender or jurisdiction, and keep a copy.

Phase 2: Framing

Framing is where the house takes shape and where layout errors show up. Walk it with your plans and a laser measure.

  • Room dimensions, ceiling heights and wall locations match the plans.
  • Window and door rough openings are the right size and height.
  • Headers, beams and point loads are supported down to the foundation as designed.
  • Sheathing is nailed per the plan, and hurricane ties or straps are installed where specified.
  • Blocking is in place for grab bars, TV mounts, cabinets, handrails and heavy fixtures.
  • Lumber is not excessively wet if the frame has been rained on; check with a moisture meter.
  • House wrap or weather barrier is lapped correctly, with windows flashed shingle-style so water runs out, not in.

Phase 3: Pre-drywall (MEP rough-in)

This is the single most valuable inspection window. Plumbing, electrical and HVAC are all visible. After drywall, every fix means cutting holes.

Plumbing

  • Drain lines are sloped, supported and protected with nail plates where they pass through studs.
  • Supply lines are secured and any required pressure test has been completed.
  • Shower valves are at the right height, and tub and shower drains line up with fixtures.

Electrical

  • Boxes are where you want outlets, switches and lights, including island and exterior outlets.
  • Low-voltage, data and any smart-home pre-wire is in place (see our smart home pre-wire guide).
  • Cables are stapled, protected and not pinched by framing.

HVAC

  • Ducts are supported, connections are sealed with mastic or approved tape, and flex duct is not crushed or kinked.
  • Return air paths exist for closed bedrooms.
  • Bath and kitchen exhaust fans vent to the outside, not into the attic.

Pro tip: Video-walk every room before insulation, slowly panning each wall from floor to ceiling while saying the room name out loud. Years from now, when you want to hang a heavy mirror or find a pipe, that video is gold.

Phase 4: Insulation

Insulation is often its own inspection, especially where energy code requirements apply. In Texas heat, a gap here shows up on your cooling bill for decades. Our post on energy-efficient building in the Texas heat goes deeper.

  • Wall batts fill cavities fully, without compression, gaps or voids around wiring and boxes.
  • Penetrations through top plates and exterior walls are sealed.
  • Spray foam, if used, is consistent in depth and coverage.
  • The attic hatch or pull-down stair is insulated and weatherstripped.
  • Attic insulation depth markers are visible and the depth matches what the plans call for.

A thermal camera can reveal missing insulation or air leaks after drywall, especially on a hot afternoon when the temperature difference is large.

Phase 5: Final inspection

At final, the city confirms the house is safe to occupy. Your own final walk should go further, building a punch list for the builder or subs. See our new construction walkthrough punch list for a room-by-room version.

  • Test every outlet with an outlet tester, including GFCI and AFCI protection where required.
  • Run every faucet, shower and toilet, and check under sinks for leaks.
  • Run the HVAC and check supply temperatures at each register.
  • Open and close every door and window; check locks and weatherstripping.
  • Look at exterior grading, gutters and downspouts to confirm water drains away from the foundation.
  • Check the roof, flashing and attic from a safe vantage point.
  • Confirm smoke and CO alarms are installed and working.

What to do when something fails or looks wrong

A failed city inspection is normal on a new build and not a reason to panic. The inspector leaves a correction notice listing what needs to change. Send it to the responsible sub the same day, agree on a fix date, and schedule the re-inspection once the work is done. Do not let the next trade cover the area until it passes.

For issues you or your private inspector find that are not code failures, such as sloppy workmanship or a detail that does not match the plans, put the request in writing with photos. Be specific about what you want corrected and by when. Keep the conversation professional; most subs will fix a clear, documented issue quickly, especially before their final payment or lien waiver. If a disagreement involves structural or engineered elements, ask your engineer for a written opinion rather than arguing it out on site.

Photo documentation tips

  • Shoot wide, then close. A wide shot shows which wall you are on; a close-up shows the detail.
  • Include a reference. Put a tape measure in the frame so you can estimate distances later.
  • Name folders by phase and date. For example, "2026-03 pre-drywall, kitchen".
  • Keep inspection results with photos. Store green tags, correction notices and private reports together.
  • Share selectively. Send photos of issues to the responsible sub with a short written note and a requested fix date.

Good records help with lender draws, warranty claims and, if it ever comes to it, insurance claims.

Next steps

Line up your inspection dates with our new home construction timeline, and pack your site bag using the essential tools for owner-builders list. For step-by-step guidance on managing your build, check out our free training.

Frequently asked questions

Do I need a private inspector if the city already inspects my new home?

You are not usually required to hire one, but many buyers and owner-builders do. City inspectors check for code minimums on a tight schedule, while a third-party inspector you hire works for you and can look at workmanship and details the city may not cover.

When is the most important time to inspect a new build?

Many experienced builders point to the pre-drywall stage. Plumbing, wiring, HVAC ducts, framing and blocking are all visible, and problems are far cheaper to fix before insulation and drywall cover them.

Who inspects new homes in Texas?

Code inspections are handled by the city, or in some unincorporated areas by the county or a third-party code inspection firm, depending on local rules. Private home inspectors in Texas are generally licensed through the Texas Real Estate Commission (TREC); confirm a license on the TREC website before hiring.

How many phase inspections should I schedule with a private inspector?

A common approach is three: pre-pour (foundation), pre-drywall, and final. Some people add a framing-only visit or an 11-month warranty inspection before the builder warranty window closes.

Written by Jonathon

Founder of New Home Investing Knowledge. Jonathon has spent more than a decade helping Texans plan, build and invest in new homes — including people acting as their own general contractor.